Time and materials vs. fixed fee contracts differ in one main way: who pays when a job takes more labor hours than estimated. Under a time and materials (T&M) contract, the client pays the actual costs of every hour worked and all materials used, so the contractor gets paid for the extra hours but has to prove each one.
Under a fixed fee contract, both sides agree on the final price before the project begins, so the contractor keeps the savings when the job runs well and absorbs cost overruns when it doesn’t. Both depend on accurate field hours.
This guide is written for specialty contractors and self-perform general contractors billing their own crews’ labor. These are the two common contracts you’ll sign most often, and each one exposes bad labor data at a different moment.
What Is a Time and Materials Contract?
A time and materials contract pays the contractor fixed hourly labor rates plus the cost of materials required to do the work. Federal rules under FAR 16.601 describe the hourly rate as covering wages, overhead, general and administrative expenses, and profit, with materials paid at actual cost.
Most construction contracts written this way include a not-to-exceed clause, a ceiling the contractor can’t bill past without approval. Setting not-to-exceed limits in time-and-material contracts protects the client’s project budget while keeping the flexibility that makes the time and materials model useful for uncertain scope. Daily T&M tickets, signed in the field, document the hours and individual expenses behind each invoice.
What Is a Fixed Fee Contract and How Does the Fixed Price Model Work?
A fixed fee contract, also called a lump sum or fixed bid, sets one total cost for the defined scope of work. Under FAR 16.202-1, a firm fixed price contract isn’t adjusted based on the contractor’s actual cost experience, so the contractor keeps any savings and pays for any overrun.
The fixed price model bundles labor, materials, contingency, and profit into the project’s total cost. Labor hours are the most fragile assumption in that number. Contractors who have completed similar projects and kept verified time records estimate those hours with far more confidence.
Time and Materials vs. Fixed Fee: Key Differences in Construction Contracts
Factor | Time and Materials | Fixed Fee |
How you get paid | Hourly rates plus actual costs of materials | One agreed final price |
Who carries labor-hour risk | Client | Contractor |
Budget certainty | Low until the project runs its course | High from day one |
Documentation | Every hour needs backup | Lighter for billing, critical for margin |
Unexpected changes | Absorbed in the hourly billing | Require change orders and price adjustments |
When bad labor data costs you | At invoice review | At closeout |
Pros and Cons of Time and Materials Contracts
Pros of Time and Materials Contracts
- Scope can change without renegotiating the whole contract.
- The contractor gets paid for the work performed.
- Work starts sooner because rates take less time to agree on than a full scope.
- The model works best when the owner values ensuring transparency, since every billed hour is visible.
Cons of Time and Materials Contracts
- The client has open-ended exposure, which is why most T&M agreements carry a ceiling.
- The contractor carries a heavy documentation load, and the client can challenge any hour without clear backup.
Pros and Cons of Fixed Price Contracts
Pros of Fixed Price Contracts
- A fixed budget makes the contract easy to approve and finance.
- Contractors who run efficient crews keep the difference as profit.
- Billing follows a predictable schedule.
Cons of Fixed Price Contracts
- Underestimated hours come straight out of margin.
- Scope gaps lead to arguments over what the original contract terms covered.
- Any changes need formal change orders before the work can be billed.
Who Absorbs Bad Labor Data Under Each Contract Type?
The contract type decides who pays for inaccurate hours and when the problem shows up. On a jobsite, labor data quality matters as much as scope.
On T&M Jobs, the General Contractor Disputes Hours It Can’t Verify
If labor backup is thin, the general contractor or owner can reject the billing, and payment terms reset. Apache Industrial Services, a specialty contractor with roughly 6,000 field employees, faced this pattern on T&M projects running over 10,000 man-hours a day. Classifying verified time by cost code and location gave its customers data they could check.
Jason Barron, Director of Project Controls, said: “SmartBarrel saved us a ton of time and money.” Read the full Apache Industrial T&M billing case study.
On Fixed Price Jobs, Overruns Stay Hidden Until Substantial Completion
Clients rarely review hours on a fixed price job, so a few extra minutes per worker per day can add up over months of work. Most contractors see the full effect at substantial completion, when it’s too late to recover the margin.
See how verified hours back up every T&M invoice. Request a SmartBarrel demo.
Fixed Fee vs. Time and Materials: When Does Choosing Fixed Price Make the Most Sense?
Choosing fixed price makes the most sense when the project scope and project requirements are clear and your historical labor data is reliable. Time and materials is the right model when scope is uncertain and you can document every hour. Your project goals and risk tolerance settle the rest.
Choose a Fixed Fee for a Defined Scope and a Fixed Budget
A well-defined scope, repeat work types, and accurate records from similar projects let you price labor with confidence and protect profit.
Choose Time and Materials for Uncertain Scope and Complex Projects
Renovations, repairs, unforeseen site conditions, and complex projects where the materials required aren’t known yet fit the materials model better. FAR 16.601 allows T&M only when costs can’t be estimated with reasonable confidence, which is a useful test for any particular project.
How a Hybrid Approach Splits Contract Terms on One Project
On many jobsites, one crew works under two sets of contract terms in the same week:
Work type | Contract terms | Where hours belong |
Base scope | Fixed fee | Base scope cost codes |
Change orders | T&M | T&M cost codes |
Unforeseen conditions | T&M | T&M cost codes |
That split is where money leaks. If T&M hours get coded to base scope cost codes, they can’t be billed, and the fixed fee job absorbs labor it wasn’t priced for. Accurate cost code assignment at the end of each shift plays a crucial role in keeping both scopes profitable.
Protect margins on fixed fee and T&M work. Book a SmartBarrel demo.
How Accurate Time Tracking Protects Margins on Both Contract Types
Both contract types depend on the same input: verified hours, tied to the right cost codes, captured as the work happens. SmartBarrel was built to capture that input and give contractors the most accurate time from the field.
- Workers clock in on the TimeClock 4.0 or the mobile app with AI-powered facial verification, which self-learns each worker and works with gloves, hardhats, safety glasses, dirt and dustfaces. No photoshoot or photo upload is required.
- Built-in LTE sends hours in real time, without waiting for WiFi.
- Foremen assign or split cost codes on the dashboard, keeping T&M and base scope time separate.
Those records feed SmartBarrel’s construction labor cost tracking software, so project costs reflect verified time whether you run one site or fifty.
Pick the Right Contract by Trusting Your Labor Data
Choosing between time and materials vs. fixed fee comes down to who carries labor-hour risk. Both models offer distinct advantages, and the potential risks in each trace back to the same hours. Fixed fee rewards contractors who know their labor numbers, while T&M pays contractors who can prove them. Verified hours help you avoid disputes on T&M work and show whether each fixed fee project meets its budget.
Get the most accurate time from the field. Request a SmartBarrel demo.
Frequently Asked Questions
How does a cost plus contract compare to time and materials?
A cost plus contract reimburses the contractor’s actual costs plus an agreed fee or percentage. A T&M contract pays fixed hourly rates that already include overhead and profit, with materials billed at cost. Both shift financial risk to the client and require detailed records.
What is a guaranteed maximum price (GMP) contract?
A GMP contract reimburses the contractor’s actual costs plus a fee, up to a ceiling agreed before work starts. Costs above that ceiling fall on the contractor, which makes GMP a middle ground between cost plus and fixed fee. Like T&M, it requires detailed cost and labor records to track spending against the cap.
How long should contractors keep the time records behind T&M billing?
The Department of Labor’s FLSA recordkeeping rules require employers to keep time cards for at least two years and payroll records for three. Construction contracts and audit clauses may require longer retention. Check your contract terms before discarding any T&M backup.